Measure Management

The FACTON measure management enables you to depict the progress from the cost saving idea to the concrete measure, including its master data administration and the analysis of cost scenarios. The individual measures of your purchases help increase the efficiency.

In FACTON, you can detect technical and commercial consequences of decisions made in the production development process and take measures to reduce costs early on. You can also add information to the measures regarding the measure type, the responsible person and the time period for achieving the target.

Measure Management in FACTON:

  • Simulation of the costs and measure implementation control according to various implementation levels and time horizons
  • Definition of technical and commercial measures for cost optimization within the cost calculation
  • Transparent overview of the actual costs, target costs, deltas and the impacts of the measures
  • Central definition and development of an own database containing frequently recurring master data measures

Measure Evaluation Scenario:

You can simulate and control the cost-based measures depending on their implementation level for each created should cost calculation. The following measure evaluation scenarios are available on calculation level:

Should Cost Calculation ► Details view ► Technical Data view schema ► Measure Evaluation Scenario

Measure Evaluation Scenario Description
IL 4-5 This scenario considers all measures from IL 4 to IL 5.
IL 3-5 This scenario considers all measures from IL 3 to IL 5.
IL 2-5 This scenario considers all measures from IL 2 to IL 5.
IL 1-5 This scenario considers all measures from IL 1 to IL 5.
Without Measures This scenario considers no measures.
IL = Implementation Level

Whether a measure is relevant for the selected measure evaluation scenario is indicated by the »Measure is Relevant/Relev for Calc: « checkbox at the technical or commercial measure. For this purpose, the effective date of the measure must be within the production period (SoP and EoP) of the calculation.

Hint

Use the Used Objects view view for an overview on technical and commercial measures used in a calculation.

Implementation Level

The implementation levels represent a certain kind of project milestones. They demonstrate how soon the planned effects (e.g. planned cost savings) are to be realized. Thus, they offer status information on an activity forecasting which can also be monetarily evaluated.

In FACTON, you can evaluate technical and commercial measures alongside a predefined implementation level logic for tracking the cost cuttings:

Implementation Level Description
<none> No implementation level
IL1 – Idea defined Idea for a measure or planned cost savings defined → Waiting for release
IL 2 - Released for implementation Release for implementation granted → Estimating the savings to be expecte
IL 3 - In implementation Concrete activities for implementing the measure defined → Implementation in progress
IL 4 - Implemented Measure implemented → Savings can now be quantified
IL 5 - Cost-effective Receipts booked → Savings can now be measured

Measure Type

The following measure types can be determined for technical and commercial measures:

Implementation Time Horizon Example Definition
<none> No implementation time horizon
Short-Term Up to one year (operative)
Mid-Term Two to three years (tactical)
Long-Term Over more than three years (strategical)
Note

The definition for the implementation time horizon terms can differ according to the company context.

Measure Value

The measure value defines which cost or time savings can be achieved with this measure. The value can impact the calculation of the respective higher-level element.

Depending on the element, the following measure values can be maintained:

  Higher-Level Element (Quantity Type) Measure Value
Commercial Measure Material (»all«) Measure Value Price per Unit
Technical Measure Material (»all«) Measure Value Material Net Quantity
Technical Measure (cycle) Measure Value Cycle Time
Technical Measure (lot) Measure Value Process Setup Time