Cost Centers

Cost centers can only be created, linked and edited in Data Administration.

Further Information

Cost Centers

Assign Cost Centers

  • Assign a process to the routing.
  1. Select a process in the project structure.
  2. In the ribbon, click on StartInsert Component ("Edit" group) Cost Center. The Cost Center Assignment dialog opens.

    Alternative: Alternatively, you can open the dialog via the context menu in the project structure.

  3. Select a cost center from the "Available Cost Centers" or from the "Cost center ID" list.
  4. Insert the selected cost center into the process by clicking Insert.
  5. Click OK.