Relevant Quantity
The relevant quantity (Rel. Qty.) represents a procurement quantity (relevant for costs and calculation).
The relevant quantity is the quantity and cost related connection between two elements. The quantity states how much one element needs/consumes from the other element. The relevant quantity is always entered in a physical unit.
Relevant Quantity = Quantity of the embedded element per quantity of the consuming element.
20MnCr5 has a relevant quantity of »0,16 kg/pc«, i.e. 0.16 kg of the material »20MnCr5« is required per 1 Piece (pc) of the Part »Motor Shaft«.
General Example | Price | Rel. Qty. | Qty. Type |
---|---|---|---|
4 EUR / pc | Piece (pc) | ||
4 kg / pc | |||
1 EUR / kg | Mass (kg) |
In technical terms is the »Relevant Quantity« an allocation.
Display of the Relevant Quantity
The relevant quantity is displayed in the following view schemes of the Structure view:
- View schema »Production Cost - Detailed«
- View schema »Input View«
The relevant quantity is displayed in the Details ► Calculation view schema (combobox) of the following calculation elements:
- Assembly
- Part
- Material
- Machine
- Process
- Worker
- Setup Process
- Setup Operator