Special calculation mode

In the Special calculation mode, the unit costs, machine costs and setup costs are determined in detail on the basis of work time values.

The Special mode is available for:

  • Processes

The following costs are included in the Special calculation mode:

  • Process: Manufacturing costs
  • Process: Setup costs

The Special mode is displayed in the calculation overview in rows colored in brown:

Calculation overview (excerpt)

Figure: Calculation overview (excerpt)

Assign the Special calculation mode with validities

Activating the validities in the system settings, enables the Advanced calculation mode to be shown in an expanded view. It now contains the "Validities" tab. The corresponding fields ("Cycle times" and "Cavities") are deactivated in the "Validities" tab. It shows the value of the currently set calculation year.

  • You can enter validity-based manufacturing parameters.
  • Further Information

    Calculations

  1. Select the element in the project structure you wish to set the Special mode at.
  2. In the ribbon, click on StartSet Mode ("Edit" group) Special . The Special dialog opens.
  3. Switch to Validities tab.
  4. Activate the "Use validities" checkbox. The activity types with respective properties are shown in the table after the project years.
  5. Define the time units in the "Unit" column.
  6. Define the machine, working and setup times along with further validity values in the "Project year" columns.
  7. Confirm your entries with OK.