Additional Costs 
Additional cost are additional process costs related to manufacturing. The costs are not included in the manufacturing of a component but are assigned to the component by creating allocations. For example for:
- Development and engineering
- Testing methods
- Prototyping
- Cost of Packaging
- Administration costs
Additional costs can be allocated to external cost objects using a specified key.
The FACTON settings allow you to choose whether to calculate additional costs on parts and/or operations.
- see System Settings, Additional Costs
Additional costs can only be created, linked and edited in Data Administration.
- see Data Administration, Additional Costs
Show additional costs
-
Select the calculation element Additional costs
in the project structure.
In the project view, additional costs are shown at the individual calculation element level.

Figure: Project Structure, Additional Costs