"Special" tab

Figure: "Data Administration" dialog, "Work Steps" category, "Special" tab
"Assignments" group
Option | Description | |
---|---|---|
![]() |
Workers | Multiple workers can be added and multiple ones can be actively assigned. When assigning a work step in the project, you can activate the "Restricted selection" checkbox in "Work Step Assignment" dialog. Doing so will only display the work steps that are linked to the highlighted worker. |
![]() |
Machines | Multiple machines can be added and multiple ones be actively assigned. When assigning a work step in the project, you can activate the "Restricted selection" checkbox in "Work Step Assignment" dialog. Doing so will only display the work steps that are linked to the selected machine. |
"Other Parameters" group
Entry field | Description | |
---|---|---|
Count | Enter the number of workers | |
![]() |
Single Time | The period of time required to carry out the work step. |
Total Time | The total time results from the product of count and single time |
"Time Value Assignment" group
Option | |
Worker + Machine | Assign the single time value to a machine and a worker |
Workers | Assign the single time value to a worker |
Machine | Assign the single time value to a machine |
Checkbox | |
Setting-up time value | When this checkbox is activated, the single time value can be used as setup time in the project |
Further Information
- Assign master data
- Worker, "Special" tab
- Machine, "Special" tab
- Rights on Data Objects