"Technology" calculation mode for additional costs

"Technology" calculation mode for additional costs

  1. Select the additional cost element in the project structure you wish to assign Technology mode to.
  2. In the ribbon, click on Start > Set Mode ("Edit" group) > Technology .
  3. The "Technology" for additional costs dialog opens.

  4. Complete the input fields in the "Technology parameters" group.
  5. Click Calculate.
  6. Confirm your entries with OK.
WARNING

After assigning a mode and executing the technology program, the calculated values will be saved. During the next calculation of the project, only the saved values will be used for computing costs.

A change in the technology program does not automatically induce in a change in the costing result.