Use the MSR value in costing

By default, the calculated MSR value is not applied to the cost calculation. By using the costing scheme, the MSR value can be:

  • defined as part of a total line (e.g. production costs)
  • subject to additional surcharges itself (as part of a total line).

MSR value as part of a total line

  1. In Data Administration, switch to the category Basic dataCosting scheme Surcharge rates.
  2. Navigate to the group which the MSR value should apply to.
  3. In this group, create the MSR value as a new surcharge rate with surcharge type "Definition" and as a surcharge on "Direct material surcharge costs".
    Data Administration dialog, Basic dataSurcharge rates

    Figure: Data Administration dialog, category Basic dataSurcharge rates

    Hint
    1. Navigate to the hierarchically lowest group of type "Total line product" (e.g. prime costs)

      Data Administration dialog, Basic dataCosting scheme

      Figure: Data Administration dialog, category Basic dataCosting scheme

  4. In this group, add a new group (if not already existing) named "Production costs". Set the group’s type to "Total line part".

    Data Administration dialog, Basic dataCosting scheme

    Figure: Data Administration dialog, category Basic dataCosting scheme

  • In the "Production costs" group, create a new group (if not already existing) named "Material costs". Set the group’s type to "Definition".

    Data Administration dialog, Basic dataCosting scheme

    Figure: Data Administration dialog, category Basic dataCosting scheme

  • In the "Production costs" group, create the surcharge rate named "Material surcharge rate" of surcharge type "Definition" on "Direct material surcharge costs".

    Data Administration dialog, Basic dataCosting scheme (tree structure)

    Figure: "Data Administration" dialog, category Basic dataCosting scheme (tree structure)

  • The surcharges that apply to the MSR value will now be included in the production costs.

    MSR value with additional surcharges

    1. In Data Administration, navigate to the sub-category "Costing scheme" of "Basic data" category.
    2. If you have not yet created the MSR value as a surcharge rate, repeat steps 2 and 3 of the previous section "MSR value as part of a total line".
    3. Create a new surcharge rate in the "Costing scheme" category. Select "Percentage" as "Surcharge type" and define the "Surcharge on" as "Direct material surcharge costs".

      Example

      Create a surcharge named "Material surcharge rate percentage".

      Data Administration dialog, Basic dataCosting scheme

      Figure: Data Administration dialog, category Basic dataCosting scheme

  • In Data Administration, navigate to the "Basic data types" sub-category under the "Basic data" category.
  • Create a new basic data entry.
  • Switch to the "Special" tab and assign a "Location" origin to the basis data type.

  • In the "Other Parameters" group, enter any values for the different calculation years. Double-click in the corresponding row to edit the percentages.

    Example
    1. Create a new basis data type named "Test basis data type" .

    2. In the "Special" tab, add a new link to the test location.

      Data Administration dialog, Basic dataBasic data types

      Figure: Data Administration dialog, category Basic dataBasic data types

  • For the years 2013, 2014 and 2015, enter a percentage value for the basic data type "Material surcharge percentage".

    Data Administration dialog, Basic dataBasic data typesTest basic data type, Special tab